1. What are the differences between Project and Production? Explain the different phases of a Project development Cycle.
2. What are the different organisation structures recommended for project organisation and what are their advantages and disadvantages?
3. Explain the PERT/COST system and Project control curves.
4. Explain the benefits of computerization of project Management (PM). Briefly describe the features you would expect to find in an integrated software package.
5. The following data is given for a PERT p Network
| Activity: | 10-20 | 10-30 | 20-30 | 20-40 | 30-40 | 30-50 | 40-60 | 50-60 |
| Time: (days) |
1-1-2 | 6-8-12 | 2-4-5 | 3-4-6 | 0-0-0 | 3-5-6 | 4-6-10 | 2-3-5 |
a) Draw the Project Network
b) Identify the critical path
c) What is the probability of completing the project within 19 days