MS-52 Project Management Question Paper

MBA - Master of Business Administration

Note: There are two Sections A and B. Attempt any three questions from Section A. All questions in Section A carry 20 marks each. Section B is compulsory and carries 40 marks.

1. A project is different from routine and regular activities. Draw a list of characteristics and distinguish the projects from other activities.

2. A project comprising of eight tasks (A to H) has the following characteristics:

Tasks Predecessor Time duration (weeks)
Optimistic Most Likely Pessimistic
A None 2 4 12
B None 10 12 26
C A 8 9 10
D A 10 15 20
E A 7 7.5 11
F B,C 9 9 9
G D 3 3.5 7
H E,F,G 5 5 5

(a) Calculate the time duration of each activity and the variance.

(b) Draw the network diagram, determine the critical path and mark in the network. What is the total project duration?

(c) What is the probability of achieving the project within the deadline of 30 weeks?

3. How does resource leveling differ from resource allocation? Discuss various methods of resource leveling in project management.

4. Contract planning and contract negotiation stages are usually located in a control project office and contract administration is done at remote construction sites. What are the disadvantages of this distance gap?

5. What are the factors, which control the cost of a project? Discuss briefly on each. How does time over-run affect the project cost?

6. Write short notes on three of the following:

(i) Advantages of matrix organisation
(ii) PERT time estimate
(iii) Total float in the project network
(iv) Crashing of project
(v) Project management software packages
(vi) Quality control in project management

SECTION B

7. (a) What are the objectives of project management information system? (b) The time and cost estimates of different activities of a project and their precedence relationship are ' given below:

Activity Preceding activity Time (weeks) Cost (Rs.)
Normal Crash Normal Crash
A –– 6 4 10,000 14,000
B –– 4 3 5,000 8,000
C A 3 2 4,000 5,000
D B 8 3 1,000 6,000
E B 14 6 9,000 13,000
F C,D 8 4 7,000 8,000

Overhead costs amount to Rs. 1,000 per week. It is stipulated that the contractor will have to pay a penalty of Rs. 2,000 per week for completing the project beyond 16 weeks

(i) Show the critical path in the network Diagram.

(ii) Find out the cost slope for every activity using normal and crash date for time and cost.

(iii) Crash the project to 16 weeks, Estimate the total cost of crashing.

Share and Recommend